There is nothing more frustrating than your new code strugling to do some task that wasn’t even supposed to be so complex.
You can use some trick like snippet below:
Sub OptimizeVBA(isOn As Boolean)
Application.ScreenUpdating = Not isOn
Application.Calculation = IIf(isOn, xlCalculationManual, xlCalculationAutomatic)
Application.EnableEvents = Not isOn
ActiveSheet.displaypagebreak = Not isOn
End SubIt can help you sometimes but when you manipulate a lot of data in excel sheets, there is another problem: abstraction. It was meant to be something good, but, there is a lot hidden in a simple operation of assigning a value into a cell, so if you execute the snippet below, that fills 1 million of cells with random numbers (which in any programming language would take a fraction of a second, it could take several seconds, depending on you hardware configuration).
Sub randomNumbers()
Randomize Timer
Dim i As Integer
Dim j As Integer
Dim t As Double
t = Timer
For i = 1 To 1000
For j = 1 To 1000
Sheets(1).Cells(i, j) = Int(Rnd * 1000) + 1
Next
Next
Debug.Print Timer - t & " seconds elapsed."
End SubWell, the code above took me 103.25 seconds on a 4th gen Intel i3 and 36.38 seconds on a 6th gen i7.
Let’s take another approach. You can do the same task assigning the values into a memory array and then assign the array itself into a range of cells.
Sub optimizedRandomNumbers()
Randomize Timer
Dim i As Integer
Dim j As Integer
Dim arr(1 To 1000, 1 To 1000) As Integer
Dim t As Double
t = Timer
For i = 1 To 1000
For j = 1 To 1000
arr(i, j) = Int(Rnd * 1000) + 1
Next
Next
Sheets(1).Cells(1, 1).Resize(1000, 1000) = arr
Debug.Print Timer - t & " seconds elapsed."
End SubWow! The code above took me 2.75 seconds on the 4th gen i3 and 1.04 second on the 6th gen i7. (And yes, I know that we usually work with 0 based arrays)
This huge difference is because Excel abstracts so much stuff into the simple operation of assigning a value into a cell like cell formats, data typing, etc. that assigning some data into a cell individually, it takes all those processing that can be done at once when you assign an entire array into a range.